Date Reported: 01/12/2013

Location: 328 Tipton St

Condition: Off buffalo rd starting at 328 tipton st.Im a home owner at 328 tipton st and the entire st. running maybe 150 yards west to east vice versa is level with man hole lids above the road itself 6 -8 inches with 20 30 pot holes roughly patched or not at all.T

Corrected? YES | Reported by: Matthew Kinslow

Date Corrected: 1/17/2013 | Time Corrected: 9:00 am | Corrected By: Shane, Todd, Tim, Marlon

Action Taken: Took a riser off to lower the 6-8 inch lid, patched potholes with cold mix

Date Reported: 01/14/2013

Location: Granddaddy Road @Cedar Lane

Condition: Pothole

Corrected? YES | Reported by: Dispatch

Date Corrected: 1/14/2013 | Time Corrected: 2:00 pm | Corrected By: Billy L , Jeff, Lee

Action Taken: Patched with cold mix

Date Reported: 01/14/2013

Location: 1044 Racheal Rd

Condition: catch basin stopped up

Corrected? YES | Reported by: Kent Carvell

Date Corrected: 1/14/2013 | Time Corrected: 12:00 pm | Corrected By: Ronnie, Rodney

Action Taken: Cleaned Catch basin

Date Reported: 01/14/2013

Location: Old Armory

Condition: NA Room - Leaking and mold. Told him that part of the problem may be the ventless heater. (Dehumidifier is working in Yoga Room. Yoga roof still leaks in the northwest corner, near air conditioner, and right inside the doorway.

Corrected? | Reported by: NA participant to Beth Campbell

Date Corrected: | Time Corrected: | Corrected By:

Action Taken:

Date Reported: 01/14/2013

Location: Old Armory

Condition: Two holes in the metal roof. Almost directly over the door opening that does to the restrooms. Can't miss the holes. Thanks

Corrected? | Reported by: Mike Boulie to Beth Campbell

Date Corrected: | Time Corrected: | Corrected By:

Action Taken:

Date Reported: 01/14/2013

Location: Rotary Gym Lobby

Condition: Lobby Area is still leaking - ceiling tiles were down and we had to replace

Corrected? | Reported by: Beth Campbell

Date Corrected: | Time Corrected: | Corrected By:

Action Taken:

Date Reported: 01/14/2013

Location: Rotary Gym - Men's Restroom

Condition: First toilet - valve is leaking

Corrected? | Reported by: Todd Barnes to Beth Campbell

Date Corrected: | Time Corrected: | Corrected By:

Action Taken:

Date Reported: 01/14/2013

Location: Rotary Park - Office Gym

Condition: Still leaking at the same places on the west side and east side as what was earlier repaired.

Corrected? | Reported by: Beth Campbell

Date Corrected: | Time Corrected: | Corrected By:

Action Taken:

Date Reported: 01/17/2013

Location: 922 Hayes Road

Condition: Tile stopped up. Water beginning to wash away dirt around tile.

Corrected? | Reported by: Stanley Houghton

Date Corrected: | Time Corrected: | Corrected By:

Action Taken:

Date Reported: 01/30/2013

Location: Beurerlein Lane

Condition: Tree down across road near the bridge

Corrected? YES | Reported by: Dispatch

Date Corrected: 1/30/2013 | Time Corrected: 9:00 am | Corrected By: Daren, Marlon, Tim

Action Taken: Cut and moved tree from road


<< Start < Prev 1 2 3 4 5 6 7 Next > End >>
Page 1 of 7
New Orders
| Disclaimer | Copyright © 2013. Welcome to Lawrenceburg Tennessee Government. | Designed by Liberty Webs

Deprecated: Function ereg() is deprecated in /home/content/08/9227108/html/www2/modules/mod_s5_box/tmpl/default.php on line 17